Quest event energy insights logo

Creating clarity during the energy transition

search
    cancel (1) 1

      A living network of curious minds.

      We’re an open platform where over 100 million readers come to find insightful and dynamic thinking. Here, expert and undiscovered voices alike dive into the heart of any topic and bring new ideas to the surface.

      New call-to-action
      LOAD MORE

      Events

      March 18, 2025 | Melbourne | Australia

      EV Charging 2025

      March 31, 2025 | Sheraton Grand Sydney Hyde Park | Australia

      Australian Domestic Gas Outlook 2025

      June 17, 2025 | Melbourne Convention and Exhibition Centre | Australia

      Australian Energy Week 2025

      September 9, 2025 | Sydney | Australia

      Women in Energy & Renewables Summit 2025

      New call-to-action
      Australian Hydrogen Forum
      New call-to-action
      Generation & Storage, Transmission & Distribution — 8 mins read

      Delivering successful energy projects in the renewable revolution

      To achieve net zero by 2050, Australia’s energy landscape needs a massive, rapid step-change. The task is enormous – but so are the opportunities.

      With coal power stations expected to retire two to three times faster than scheduled, the Australian Energy Market Operator (AEMO)’s 2022 draft Integrated System Plan estimates that by 2050 Australia will need nine times the current level of renewable generation, five times the distributed solar PV generation and three times the firming capacity and storage solutions. This is just to replace retiring coal generation and doesn’t even begin to factor in a new domestic and export green hydrogen industry.

      The scale of this generation and firming deployment will require more than 10,000 km of new transmission lines to get the electricity to consumers – an enormous investment in new transmission infrastructure.

      The most efficient and cost-effective way to manage these challenges is expected to be through the development of Renewable Energy Zones (REZs), where new renewable energy and storage developments can be concentrated. REZs can provide efficiencies in the amount of transmission lines needed to connect to the grid and population centres reducing the cost to consumers, and can minimise risks for investors by potentially sharing some infrastructure and costs across multiple parties.

      The National Electricity Market (NEM) is already intricate, and overlaying state-based REZs adds further complexity. Investors and project developers will need to understand how the state-based REZ schemes interface with the NEM and AEMO rules. Of course, in such a dynamic and evolving sector, there are also many layers of uncertainty – including future regulatory and policy changes, such as the Energy Security Board’s transmission access reforms, which have the potential to impact operations and returns for investors and consumers.

      "To reap the rewards of the energy transition, participants in the sector will need a good grasp of its inherent complexities."

      These are exciting times for infrastructure investors and renewable energy developers, but it will be critical to come to grips with complexity in some key areas in order to maximise the likelihood of success and avoid preventable pitfalls. The following four areas are essential considerations right now.

      1. Getting connected

      Improving the grid connection process and making it quicker and easier to connect is key to accelerating the energy transition.

      The time it takes to develop a project and reach financial close has progressively increased and often takes more than three years – yet it only takes a few weeks to connect solar PV to a rooftop. As a consequence, the amount of distributed renewable energy added to system capacity has exceeded 3 GW for each of the past two years.

      The proposed concept and design of REZs, with their significant upgrades in transmission infrastructure, is likely to shorten the process of grid connection and reduce the likelihood of curtailment. Batching power system and connection studies, as proposed for the Central West Orana REZ, will speed up connection compared with undertaking these sequentially.

      Investments in transmission in the REZs will be essential for fast-tracking new renewable generation so it is ready to meet the accelerating timeframe of coal retirement.

      2. Supply issues across the energy value chain

      The pipeline of infrastructure projects in Australia is already significant. Adding REZs to this picture raises a burning question: will there be enough appropriately qualified personnel available to build the REZs to the expected quality and schedule? One aspect of the solution is likely to be upskilling and retraining workers displaced from industries such as coal mining. While this will be positive for affected communities, it is unlikely to be sufficient in itself to achieve the build out, so early preparation and resource planning will be essential.

      Beyond personnel, will there be enough of the necessary technologies, materials and equipment for forthcoming renewables, storage and transmission investments? It is likely that pressures will emerge right across the value chain. Giga projects such as Sun Cable’s Australia-Asia Power Link will require a huge amount of transmission lines and HVDC cables, with the quantum required potentially too great for a single supplier or even a single region. New renewables projects will need to consider alternatives early.

      Another significant challenge is availability and cost of key critical energy minerals required in renewable energy technologies. The cost of minerals such as silicon, lithium and cobalt has skyrocketed and is likely to escalate further under the pressure of the energy transition and global geopolitical dynamics.

      For projects that have already locked in their power purchase agreements (PPAs) and expected internal rates of return (IRRs), rising equipment costs and changing cost assumptions will have implications. Some solar projects have already encountered much higher than expected costs for solar panels. Who will bear the impact of these escalating costs? Will the project still be viable? This dynamic needs to be factored into a project’s expected returns and considered by potential offtakers.

      3. Giving weight to all three aspects of ESG

      Environmental and social licence can make or break a project, so it’s vital that environmental, social and governance issues remain at the front of the agenda. Mere compliance with the basic requirements of legislation is unlikely to win over a community or build a positive reputation.

      Social licence will be a key issue when developing REZs. Many of these areas currently have limited transmission infrastructure, so routes, land access and easements for new infrastructure will need to be negotiated carefully with landholders and local communities, and with a particular focus on First Nations peoples. Early engagement will be very important so that everyone can understand the scope and intended outcome of the project, potential visual or environmental impacts, alternative routes or construction methods, and possible community benefits.

      Although some examples of best practice in community engagement are beginning to emerge in Australia, there is still much to be done to build greater trust with communities across the country to support the energy transition.

      Consideration should also be given to ethical and human rights issues throughout the value chain, such as the risk that materials or components may have been extracted or manufactured under conditions of modern slavery, or other socially and environmentally harmful practices.

      4. Obtaining an offtake

      Ultimately, most projects will not secure financing or progress to construction without an offtake arrangement to underpin the revenue stream. The demand for offtake is changing. The days of the ‘big 3’ retailers being the predominant offtakers has passed, and the corporate PPA market continues to grow as companies seek to reduce emissions and control their exposure to volatile power prices.

      In NSW, it will be interesting to see the interplay of offtakes and the long-term energy service agreements (LTESAs), which will offer an option to access price guarantees for eligible generation, long-duration storage and firming projects.

      Solving for success

      A new energy paradigm is unfolding around us in real time. In this rapidly evolving energy market, there will continue to be complexities, unknowns and risks for investors and developers. However, none of the challenges we’ve discussed in this article are insurmountable, and they shouldn’t overshadow the excitement of the sector’s opportunities. Early awareness of these considerations will go a long way towards more positive project outcomes.


      About the author

      Fiona McIntyre is a Partner in PwC Australia’s Integrated Infrastructure - Environmental Transactions & Advisory team. Fiona provides lead financial and commercial advisory services to clients in the infrastructure, energy & utilities sectors, with a strong focus on renewables. She joined PwC in 2022 and prior to this was National Australia Bank’s Global Head of Energy & Utilities, Corporate & Institutional Banking and led that team for 15 years.

      Fiona McIntyre, Partner, Integrated Infrastructure | Environmental Transactions & Advisory, PwC

      Energy Monthly

      Group (2)

      Get a different perspective on energy with our monthly newsletter.

      New call-to-action
      March 18, 2025 | Melbourne | Australia

      EV Charging 2025

      March 31, 2025 | Sheraton Grand Sydney Hyde Park | Australia

      Australian Domestic Gas Outlook 2025

      June 17, 2025 | Melbourne Convention and Exhibition Centre | Australia

      Australian Energy Week 2025

      September 9, 2025 | Sydney | Australia

      Women in Energy & Renewables Summit 2025

      New call-to-action